2 FERNTREE PLACE | CONSTRUCTION UPDATE, Feb 2021

The following activities were achieved in February 2021 from builder Hansen Yuncken.

  • Completion of 100% of the excavation, with levels in most of the basement at the base of B2.

  • Completion of 100% of the shotcrete walls and ground anchors in all basement walls.

  • Completion of the hardstand around the site.

  • Tower Crane base poured & Tower Crane erection completed.

  • Pad footings in B2 poured – approx. 50%.

  • Installation of In-ground services.

Photos included show progress of the basement construction and erection of tower crane.

In March the structure will commence including the completion of all footings, ground slab and the structural columns will commence erection.